The technical meeting was moved from 23 March to 30 March.
Cortus, Q Power and BEIC participated.
After input from Höganäs Sweden AB, the final location for the pilot plant was decided. The interfaces regarding electricity, signal (monitoring and control), synags, reject water, flue gases and saftey gas (CO2) were discussed.
The aim is to start the pilot testing in September, one month before schedule, to not interfer with the Biomethaverse project, which starts 1 January 2024.
Next technical meeting will be at 13:00 on the 14th of April.