Project Consortium Meeting 12 June

The SynFerm consortium meeting took place as an online meeting on the 12th of June. Biokraft, Cortus, Q Power and BEIC were represented.

The high-pressure storage hs been filled with syngas and the pressure is currently 133 bar. The biological methanation plant has been fed with syngas successfully for two weeks. The initial feeding rate was 5 L/min but later it was ramped up to 12 L/min. Currently there is a technical problem with a gas analyzer. The supplier has been involved to sort out the problem.

The next project consortium meeting is scheduled to the 16th of August at 10:00 CEST as an online meeting.