Project Consortium Meeting 16 August

The SynFerm consortium meeting took place as an online meeting on the 16th of August. Biokraft, Cortus, NSR, Q Power and BEIC were represented.

Several test runs have been conducted during the summer. Initially there was some problems with a CO analyzer but it was replaced in the beginning of July. Since bottled hydrogen was available, a test run with hydrogen addition was conducted, even though it was not part of the project application.

The biological methanation pilot plant will be dismantled and returned back to Finland at the end of August.

The next project consortium meeting is scheduled to the 20th of September at 13:00 CEST as an online meeting.