The technical meeting was moved from 14 April to 21 April and later to 28 April to ensure that the participant organisations, Cortus, Q Power and BEIC, had signed the Consortium Agreement.
The documentation related to the pilot plant has been translated from Finnish to English by Q Power. Cortus has placed the order regarding the 1,000 Nm3 high pressure storage system and the expect delivery is in August.
Practical details such as odorisation and the potential impact on the biological methanation, and effluent water management were discussed.
The next Technical Meeting is scheduled to 11 May at 10:00-12:00.