Project Consortium Meeting 13 April

The SynFerm consortium meeting took place as an online meeting on the 13th of April.
All the project partners were represented.
The  last details of the Consortium Agreement (CA) were discussed.
Electronic signing of the CA is expected next week.
The pilot testing will be advanced in time 1 month (i.e., start installation 1 September instead of 1 October) to ensure some marginal to a subsequent project at the Höganäs site.

The next project consortium meeting will take place on the 22nd of May at 10:00 CEST.