Project Consortium Meeting 5 October

The SynFerm consortium meeting took place as an online meeting on the 5th of October.
Biokraft, Cortus, Q Power and BEIC were represented.

The Q Power´s mobile pilot scale biological methanation unit has been modified (re-routing of cables and pipes, connecting sensors to the PLC system etc.) to have the two containers in series instead of parallel. The pilot plant is now undergoing testing to check that the modifications are OK. The pilot plant is scheduled to arrive to Höganäs on the 16th of October.

The next project consortium meeting is scheduled to the 7th of November at 10:00 CET as a hybrid meeting (both physical and online participation) at Cortus’ site in Höganäs.